Velocity

Velocity = Projected amount of story points which a team can burn over a set period

A development team’s velocity using Scrum or Kanban can be worked out by totalling up the amount of points which has been burned across 3-5 sprints/set periods and then dividing it by the periods the totals were calculated over (taking an average across the periods).

It’s important to use an average across the last 3-5 periods, so then holiday seasons and a sprint where items have moved over to the following sprint doesn’t dramatically impact the numbers as much as it would if you only looked at the last period.

A team can use their velocity in many ways, for example:

  • Understanding how many points they can commit to during sprint planning/work out how many PBIs (Product Backlog Items) could be done across the next 2 weeks
  • To aid prioritisation (The ‘I’ in ROI)
  • Predicting when software can be delivered in the backlog, which can then be used to forecast future feature delivery
  • Understanding the impact on any resources eg. Scrum team member changes or adding extra teams to the product
  • Understanding the impact which dependencies are having which can be reviewed in the retro, great example being build pipelines
  • Providing a more accurate estimate than a t-shirt size
  • As a KPI for efficiency improvements

I tend to refer to points being ‘burned’ rather than ‘delivered’ because it’s quite easy to fall into the velocity/story point delivery trap of obsessing about points being delivered rather than obsessing about delivering outcomes (business value).